The Latest Dirt on our Construction Progress

by User Not Found | Aug 18, 2016

Panther Island Bridges
Work continues along Henderson Street and White Settlement as the construction of the signature Panther Island Bridges progresses. Steel has been placed, concrete foundations have been poured and soon you will see concrete poured to form the v-piers which give the bridge their signature profile. Soon, a detour will be in place along North Main Street as construction of that bridge begins. All three bridges are expected to be complete in 2018.


Gateway Park Oxbow A&C
The U.S. Army Corps of Engineers are continuing Phase One of excavations in Gateway Park Oxbow A &C. To date, the project has removed over 553,600 cubic yards of soil from the site. In total, this phase of work will remove 1.4 million cubic yards of soil. The work is expected to be complete by early 2017 and will achieve two important goals: providing additional flood protection for the entire area and making way for future recreational enhancements such as soccer fields and trailhead amenities.